Create a task

  1. In Team Planner, select + New Task. Or select + Add task at the bottom of a column.
  2. Fill in Title.
  3. Pick the Bucket (column), Priority and Due date.
  4. Pick Assignees and add Labels or Notes if you like.
  5. Select Create Task.

Change or finish a task

  1. Select Open → on the card.
  2. Change what you need and select Save.
  3. To finish it, drag it to Done.

Tasks that came from a team note or an event have Open linked item → to jump back.

See your own tasks

Under Views, select Assigned to Me. Select Completed to see finished tasks.